|
Method of Construction
Prior to beginning drilling an extensive pre-grout operation is generally undertaken to prevent environmental
problems during construction and limit groundwater flows between the shaft and the formation. By drilling
small diameter holes around the perimeter of the shaft and pressure grouting the formation it is possible to
almost completely separate the surrounding water tables from the shaft construction.
Once the pre-grout operation is complete, surface casing is set to competent rock by excavating a large enough
hole through the overburden to accept the casing and the drilling tools. This surface casing can be either
steel casing grouted in place or cast-in-place concrete depending on the size of the shaft. A concrete pad is
then generally poured to accommodate the drilling equipment and future equipment such as fans.
For holes larger than 610 mm (24 inches) diameter a pilot hole is drilled next. This pilot hole is surveyed to
determine deviation and location underground for future cut ins. The pilot hole is then reamed to a diameter
of sufficient size to accommodate the final liner. During the drilling of the pilot hole and the final reaming,
all cuttings are removed from the hole using a simple air lift system with water being the circulation media and
placed in a water tight cuttings pond constructed close to the drilling location.
Lining of these shafts is generally accomplished using either a hydrostatic steel liner
or a concrete liner. For shafts up to 2.4 m (8 feet) in diameter, hydrostatic steel liners
are easily fabricated, hauled to the site and field welded in 40’ joints. Once the liner is in place a grout
seal is pumped behind the liner to hold it in place.
3.05 m (10 foot) shafts can be either steel or concrete lined. The depth of the shaft generally determines the
economic factors which govern the liner type. Shafts greater than 3.05 m (10 feet) in diameter are almost
always concrete lined due to the enormous cost of a steel liner of that size.
nad@nadillers.com
|